Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 05/14/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
Partial pass. Electrical underground. X4 1 1/2" schedule 40 at a depth of 24". Stubbed up into new gutter box at new SES location for panel A and B to individual telephone poles feeding panels. Per key note 1. Okay to backfill progress areas. Shading required. 5/14/2025 |
| 06/24/2025 |
COT - LCEL - Electrical Progress |
|
Passed |
|