Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 01/06/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Locker rooms and shower rooms. |
| 02/13/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Lobby area soffits and fire place area. Ok to cover when Fire approves sprinkler placement. |
| 03/03/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Hallway to lobby, bar area, snack bar area, area around fire place. OK to sheet rock/patch progress areas. |
| 05/07/2025 |
COT - HCBU - Framing |
|
Passed |
|
| 12/05/2024 |
COT - HCBU - Framing |
|
Partial Pass |
Room #151 and entry hallway. Ok to insulate and cover walls. |
| 12/20/2024 |
COT - HCBU - Framing |
|
Partial Pass |
12/20/24: framing in wall at rooms 103,104,113,112,102,111 per plan ok to proceed |