Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-0723-01638
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/14/2024 | COT - HCBU - Building Progress | Partial Pass | 3/14/24: Footings from GL Z3-Z7 ok to pour. Footings from GL Z7-B7 ok to pour. | |
10/23/2024 | COT - HCBU - Building Progress | Partial Pass | ||
10/25/2024 | COT - HCBU - Building Progress | Partial Pass | 3/14/24: Footings from GL Z3-Z7 ok to pour. Footings from GL Z7-B7 ok to pour. 10/25/24: fasteners per schedule at 5/8" type-x on south demising wall per detail C ok to proceed. |
|
11/06/2024 | COT - HCBU - Building Progress | Partial Pass | 3/14/24: Footings from GL Z3-Z7 ok to pour. Footings from GL Z7-B7 ok to pour. 10/25/24: fasteners per schedule at 5/8" type-x on south demising wall per detail C ok to proceed. 11/6/24: drywall nailing per schedule at office breakroom #s-105, wear and south walls at skywest hanger. |
|
11/08/2024 | COT - HCBU - Building Progress | Partial Pass | Hanger side Z line from 7-12. Fire rated wall and parts area T- L.5 east side. Okay to proceed progress areas. 11/8/2024 | |
11/13/2024 | COT - HCBU - Building Progress | Partial Pass | 3/14/24: Footings from GL Z3-Z7 ok to pour. Footings from GL Z7-B7 ok to pour. 10/25/24: fasteners per schedule at 5/8" type-x on south demising wall per detail C ok to proceed. 11/6/24: drywall nailing per schedule at office breakroom #s-105, wear and south walls at skywest hanger. Hanger side Z line from 7-12. Fire rated wall and parts area T- L.5 east side. Okay to proceed progress areas. 11/8/2024 11/13/24: Partial drywall screwing at Parts Fire Wall at back side of Fire Riser room |