Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Above Ceiling

Date Description Inspector Results Comments
01/14/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/24: mechanical above ceiling at office area passed ok to proceed with ceiling tiles.
1/14/25: Plumbing pressure test at Shop toilet rooms
01/17/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/24: mechanical above ceiling at office area passed ok to proceed with ceiling tiles.
1/14/25: Plumbing pressure test at Shop toilet rooms
1/17/25: mechanical above ceiling in rooms 148,150,151,144 ok to insulate hard duct.
02/06/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/24: mechanical above ceiling at office area passed ok to proceed with ceiling tiles.
1/14/25: Plumbing pressure test at Shop toilet rooms
1/17/25: mechanical above ceiling in rooms 148,150,151,144 ok to insulate hard duct.
2/6/25: mechanical hard duct and spiral duct in shop area ok to insulate
02/27/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/24: mechanical above ceiling at office area passed ok to proceed with ceiling tiles.
1/14/25: Plumbing pressure test at Shop toilet rooms
1/17/25: mechanical above ceiling in rooms 148,150,151,144 ok to insulate hard duct.
2/6/25: mechanical hard duct and spiral duct in shop area ok to insulate
2/27/25: hard duct and drops in shop per plans ok to proceed with insulation
05/08/2025 COT - HCME - Mechanical Above Ceiling Passed
COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
11/22/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/2024 COT - HCME - Mechanical Above Ceiling Partial Pass 10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
10/16/24: Mechanical above ceiling partial pass for hard duct from GL N-B/1-5, 5.5/7. Ok to insulate
Vestibule S100. Electrical above door 100B and 100A above ceiling approved okay to proceed progress areas. 11/8/2024
11/22/24: M.E.P above ceiling passed at hard lid areas room 109,110 and 112.
12/13/24: electrical and plumbing above ceiling passed in all rooms in office area.
12/20/24: mechanical above ceiling at office area passed ok to proceed with ceiling tiles.