Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
Permit Number - TC-COM-0723-01638
Inspection Description - COT - HCBU - Preslab
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2024 | COT - HCBU - Preslab | Partial Pass | 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. | |
09/03/2024 | COT - HCBU - Preslab | Partial Pass | 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 9/3/24: reinforcement at north trench drain per RFI ok to proceed with pour. |
|
09/04/2024 | COT - HCBU - Preslab | Partial Pass | 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 9/3/24: reinforcement at north trench drain per RFI ok to proceed with pour. 9/4/24: Preslab reinforcement passed at office area. Ok to proceed with pour. |
|
09/10/2024 | COT - HCBU - Preslab | Partial Pass | 9/10/2024Center trench drain on grid line 14 okay for concrete placement. From grid 9.5 to 12.5 north to south and east to west is Grid line B to Z . Pad okay for concrete placement. |
|
09/18/2024 | COT - HCBU - Preslab | Partial Pass | Parts area. From M-Z. Line 3-7 Trench drain on grid line 14. East half of hanger door rails. Okay for concrete placement. 9/18/2024 |
|
09/25/2024 | COT - HCBU - Preslab | Partial Pass | 4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area. 4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete, 5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan. 5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete 5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed. 5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1 5/29/24: footing inspection at dumpster is under DP permit. 7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7. 7/24/24: loading dock stairs reinforcement per plan ok to proceed. 8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete. 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed. 8/19/24: 3 entry columns formed and ready to pour ok to proceed. Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024 9/25/24: remaining 7 light pole bases at south of project site per plan. Ok for concrete placement. Pre slab at pour 3 GL B-Z/ 12.5 -15 |
|
09/25/2024 | COT - HCBU - Preslab | Partial Pass | 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 9/3/24: reinforcement at north trench drain per RFI ok to proceed with pour. 9/4/24: Preslab reinforcement passed at office area. Ok to proceed with pour. 9/10/2024Center trench drain on grid line 14 okay for concrete placement. From grid 9.5 to 12.5 north to south and east to west is Grid line B to Z . Pad okay for concrete placement. Parts area. From M-Z. Line 3-7 Trench drain on grid line 14. East half of hanger door rails. Okay for concrete placement. 9/18/2024 3/6/24 Partial by third party 3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS 3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete 4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete. |
|
10/08/2024 | COT - HCBU - Preslab | Partial Pass | 4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area. 4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete, 5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan. 5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete 5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed. 5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1 5/29/24: footing inspection at dumpster is under DP permit. 7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7. 7/24/24: loading dock stairs reinforcement per plan ok to proceed. 8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete. 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed. 8/19/24: 3 entry columns formed and ready to pour ok to proceed. Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024 9/25/24: remaining 7 light pole bases at south of project site per plan. Ok for concrete placement. Pre slab at pour 3 GL B-Z/ 12.5 -15 10/8/24: Pre-slab reinforcement inspection at GL Z-Da/3-7.5 per plans on to proceed in progress areas. |
|
10/14/2024 | COT - HCBU - Preslab | Partial Pass | 10/14/2024 7.5 - 12. From Z line to Da. (Shop south half). Okay for concrete placement. | |
10/21/2024 | COT - HCBU - Preslab | Partial Pass | 4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area. 4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete, 5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan. 5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete 5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed. 5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1 5/29/24: footing inspection at dumpster is under DP permit. 7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7. 7/24/24: loading dock stairs reinforcement per plan ok to proceed. 8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete. 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed. 8/19/24: 3 entry columns formed and ready to pour ok to proceed. Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024 9/25/24: remaining 7 light pole bases at south of project site per plan. Ok for concrete placement. Pre slab at pour 3 GL B-Z/ 12.5 -15 10/8/24: Pre-slab reinforcement inspection at GL Z-Da/3-7.5 per plans on to proceed in progress areas. 10/21/24: south trench drains reinforced per plans ok to proceed. |
|
10/29/2024 | COT - HCBU - Preslab | Passed | 8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed. 9/3/24: reinforcement at north trench drain per RFI ok to proceed with pour. 9/4/24: Preslab reinforcement passed at office area. Ok to proceed with pour. 9/10/2024Center trench drain on grid line 14 okay for concrete placement. From grid 9.5 to 12.5 north to south and east to west is Grid line B to Z . Pad okay for concrete placement. Parts area. From M-Z. Line 3-7 Trench drain on grid line 14. East half of hanger door rails. Okay for concrete placement. 9/18/2024 3/6/24 Partial by third party 3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS 3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete 4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete. 10/14/2024 7.5 - 12. From Z line to Da. (Shop south half). Okay for concrete placement. 10/29/24: Preslab passed at room s-155ok to proceed with pour |