Inspection Status: Passed

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
01/07/2025 COT - HCEL - Electrical Underground  Passed
01/07/2025 COT - HCEL - Electrical Underground  Passed
03/28/2024 COT - HCEL - Electrical Underground  Partial Pass
04/05/2024 COT - HCEL - Electrical Underground  Partial Pass
04/11/2024 COT - HCEL - Electrical Underground  Partial Pass
05/06/2024 COT - HCEL - Electrical Underground  Partial Pass
05/15/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
05/23/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
05/29/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
06/11/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
06/13/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
06/14/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
06/25/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
07/18/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
07/19/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
07/24/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
07/30/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
08/02/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
08/06/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
08/08/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
08/14/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
8/14/24:GL/ 15.5 (2)2" conduit for panels ok to backfill , GL 17.5 1" hanger light ok to backfill, 1" and 2" conduit for gate operator and communication at GL A/13.5-8.5
08/19/2024 COT - HCEL - Electrical Underground  Partial Pass 7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
8/14/24:GL/ 15.5 (2)2" conduit for panels ok to backfill , GL 17.5 1" hanger light ok to backfill, 1" and 2" conduit for gate operator and communication at GL A/13.5-8.5
8/19/24: electric underground GL Q-Z/11 (2) 2" for panel H7 and (2) 2" for compressor 1 and 2.
08/19/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
08/23/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
8/23/24: (10)4" conduit from North East corner of building to about 150' north of building ok to backfill progress area.
08/30/2024 COT - HCEL - Electrical Underground  Partial Pass 7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
8/14/24:GL/ 15.5 (2)2" conduit for panels ok to backfill , GL 17.5 1" hanger light ok to backfill, 1" and 2" conduit for gate operator and communication at GL A/13.5-8.5
8/19/24: electric underground GL Q-Z/11 (2) 2" for panel H7 and (2) 2" for compressor 1 and 2.
8/30/24: 70' run of (10)4" conduit for secondaries ok to backfill. (North of project)
09/04/2024 COT - HCEL - Electrical Underground  Partial Pass Partial approval for chases through East Hanger footer
Partial approval for chases through West Hanger footer
Partial grid 7-9 and B-H ok to cover
Partial approval, gridlines Z to Da and 3 to 9
5/15/24: elected underground- (4) 2” and (2) 2 1/2” conduit from service entrance at GL Z/7 to GL L/7 ok to backfill. Shading required
5/23/24: (10) 4" conduit from SES to transformer( 10' run out of building going southeast). (9) 4" conduit from SES to MSB ok to backfill. Main panel feeders ok to backfill.
5/29/24: (10)4" conduit from MSB running 100' to north east corner of building to transformer. Ok to backfill progress area.
6/11/24: electrical underground per plan at Gridline 3 from L-W
6/13/24: wanted temp power inspection at office trailer. Passed ok to proceed.
6/14/24: electrical underground at offices on north east of building passed ok to backfill.
6/25/24: (2) 4" and (1) 2" conduit for Telecomm from building to terminal box at north half of project site. Ok to backfill.
7/18/24: Electrical underground per plan at North west corner of hanger GL 7-8 ok to backfill progress areas.
8/23/24: (10)4" conduit from North East corner of building to about 150' north of building ok to backfill progress area.
9/4/24: Secondary's to Transformer pad passed ok to backfill.
09/16/2024 COT - HCEL - Electrical Underground  Partial Pass Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024
09/25/2024 COT - HCEL - Electrical Underground  Partial Pass 7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
8/14/24:GL/ 15.5 (2)2" conduit for panels ok to backfill , GL 17.5 1" hanger light ok to backfill, 1" and 2" conduit for gate operator and communication at GL A/13.5-8.5
8/19/24: electric underground GL Q-Z/11 (2) 2" for panel H7 and (2) 2" for compressor 1 and 2.
8/30/24: 70' run of (10)4" conduit for secondaries ok to backfill. (North of project)
9/25/24: electrical underground passed at 7 light pole bases at south end of project site
10/16/2024 COT - HCEL - Electrical Underground  Partial Pass 7/19/24: (1)2" and (1)2 1/2" conduit from GL V-Q/7
7/24/24: electrical underground for 5 light poles north entrance of building and 3 on south east corner of project.ok to backfill progress areas.
7/30/24: electrical underground for 3 light poles on southwest corner of job site.
8/2/24: electrical underground for all 7 light poles on south end of building complete ok to backfill progress areas. Shading required.
8/6/24: electrical underground for panel H7 and compressor 1&2 from GL Q-S/10, (4)2" Low voltage conduit from GL Q/10-16 ok to backfill.
8/8/24: electrical underground (2)2" for communication GL N-B/16, exhaust fan 6 and 7, security and tarmac light electrical underground per plans at Z/3.
8/14/24:GL/ 15.5 (2)2" conduit for panels ok to backfill , GL 17.5 1" hanger light ok to backfill, 1" and 2" conduit for gate operator and communication at GL A/13.5-8.5
8/19/24: electric underground GL Q-Z/11 (2) 2" for panel H7 and (2) 2" for compressor 1 and 2.
8/30/24: 70' run of (10)4" conduit for secondaries ok to backfill. (North of project)
9/25/24: electrical underground passed at 7 light pole bases at south end of project site
10/16/24: Partial Electrical U/G at Airside Taxi Way Lights ok to proceed with slurry. .