Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0723-01638

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
03/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
03/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
03/28/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
04/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
04/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/11/24 see attached photos
04/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
05/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
05/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
05/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
05/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
05/29/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
07/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
07/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
08/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
08/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed.
08/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed.
8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed.
08/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed.
8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed.
8/19/24: 3 entry columns formed and ready to pour ok to proceed.
08/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed.
8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed.
8/19/24: 3 entry columns formed and ready to pour ok to proceed.
09/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024
09/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/6/24 Partial by third party
3/21/24 stem wall line B/3-6.8, LINE 3/B-M,N.5-X.7 AND COLUMN FOOTERS LINE 7/D-X 14 PIERS
3/28/24 partial approval for East hanger footer see third-party inspection OK to place concrete. Partial approval for tool room footer grid line 3-Z to Northwest corner, OK to place concrete
4/5/24 partial approval for East hanger footer see third-party inspection OK to place concrete.
4/18/24 Zee line 7 to 20 pedestal bases OK to place concrete, grid line DA to CA5 and 3 to 12 for stemwall OK to place concrete, partial approval for manhole base poor OK to continue in progress area.
4/24/24: Z line (8,9,10,11,12) Pedestal bases ok to place concrete (1/S82), B line (8,9,10,11,12) pedestal bases ok to place concrete, Dock stem wall and Dock retaining wall per plan ok to place concrete,
5/2/24: loading docks wall footing on north side per detail S84/44 per plan ok to proceed. Shop south wall detail S82/13 and S82/7 for 3 column pedestal footings per plan.
5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/
09/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/6/24 Grid 3 from m to n partial for stem wall, ok to place concrete
5/21/24: Partial Rebar at Loading dock pit and Hangar SE/ SW Door Pockets GL A/18-20 and GL Z/18-20. Pedestal reinforcements per plan ok to proceed.
5/23/24: foundation exterior wall reinforcement per plan at GL Da/12.1 - Ca/12.1, pedestals reinforcement per plan at GL Da/12.1, Ca.5/12.1, Ca.12.1
5/29/24: footing inspection at dumpster is under DP permit.
7/10/24:footing at GL A-Z/19 per detail S82/16 per plans ok to proceed, stem wall reinforcement per plan at GL Z-DA/12 per detail S82/13 and S82/7.
7/24/24: loading dock stairs reinforcement per plan ok to proceed.
8/2/24: CIP Column and matte slab reinforcement per plans ok to pour concrete.
8/9/24: first pour north ok to proceed. 4 columns at entry reinforcement per plan ok to proceed.
8/13/24: Anchor bolts at 4 entry columns per plan ok to proceed.
8/19/24: 3 entry columns formed and ready to pour ok to proceed.

Partial pass Total of 5 Light Pole Bases at North Parking area per plan, okay for concrete placement. 9/16/2024
9/25/24: remaining 7 light pole bases at south of project site per plan. Ok for concrete placement. Pre slab at pour 3 GL B-Z/ 12.5 -15