Inspection Status: Passed

Inspection History: COT - HCPL - Rough Soil 

Date Description Inspector Results Comments
01/06/2025 COT - HCPL - Rough Soil  Passed
05/02/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
07/10/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
07/19/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
07/30/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
08/02/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
8/2/24: Oil/water separator under test ok to backfill progress area.
08/14/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
8/2/24: Oil/water separator under test ok to backfill progress area.
8/14/24: plumbing underground from GL E/10-16 per plans ok to proceed. North trench drain GL/10 ok to proceed.
08/19/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
8/2/24: Oil/water separator under test ok to backfill progress area.
8/14/24: plumbing underground from GL E/10-16 per plans ok to proceed. North trench drain GL/10 ok to proceed.
8/19/24: 3" foot vent with cleanout for combo waste and vent GL Z-M/13 ok to backfill. Shading required.
08/21/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
8/2/24: Oil/water separator under test ok to backfill progress area.
8/14/24: plumbing underground from GL E/10-16 per plans ok to proceed. North trench drain GL/10 ok to proceed.
8/19/24: 3" foot vent with cleanout for combo waste and vent GL Z-M/13 ok to backfill. Shading required.
8/21/24: plumbing underground for floor drains from GL 19/Z-E ok to backfill ok to proceed, shading required
08/27/2024 COT - HCPL - Rough Soil  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/2/24: ok to backfill from cleanout #6 to cleanout#8
7/10/24: trench drains underground plumbing per plans from GL N-Q,X-Ab/3 ok to backfill progress area, Sewer 20' stub out at GL Ab.5/3 capped at future run, ok to backfill progress area, floor trench at GL Da/6.8-8 ok to backfill progress area.
7/19/24: 3/4" Copper Air line in 3" Sleeve under 150psi GL V/7-10 ok to backfill progress areas. Plumbing underground from future connection at oil/water separator from GL A-F/8.5-10.
7/30/24: Pending test at oil/water separator
8/2/24: Oil/water separator under test ok to backfill progress area.
8/14/24: plumbing underground from GL E/10-16 per plans ok to proceed. North trench drain GL/10 ok to proceed.
8/19/24: 3" foot vent with cleanout for combo waste and vent GL Z-M/13 ok to backfill. Shading required.
8/21/24: plumbing underground for floor drains from GL 19/Z-E ok to backfill ok to proceed, shading required
8/27/24: Plumbing underground at Mechanical room per plan ok to proceed with backfill.
09/30/2024 COT - HCPL - Rough Soil  Partial Pass From grid line 7-12. Z- BA. Room S134, S150, S151, and S152. Okay to backfill progress areas. 9/30/2024