Inspection Status: Passed

Inspection History: COT - HCPL - Sewer 

Date Description Inspector Results Comments
01/06/2025 COT - HCPL - Sewer  Passed
03/06/2024 COT - HCPL - Sewer  Not Ready
04/22/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
04/24/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
04/26/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
04/30/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
05/06/2024 COT - HCPL - Sewer  Partial Pass
05/08/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
07/24/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
7/24/24: bedding for sand oil interceptor. Pending test.
08/08/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
7/24/24: bedding for sand oil interceptor. Pending test.
8/8/24: plumbing underground per plans from GL S-E/7-3 ok to backfill
09/10/2024 COT - HCPL - Sewer  Partial Pass 9/10/2024Parts area. From north to south 3 to 7 from east to west grid line M to Z.
Okay to backfill progress areas. Shading required.
10/14/2024 COT - HCPL - Sewer  Canceled Canceled per contractor. 10/14/2024
10/15/2024 COT - HCPL - Sewer  Not Ready
10/16/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
7/24/24: bedding for sand oil interceptor. Pending test.
8/8/24: plumbing underground per plans from GL S-E/7-3 ok to backfill

9/10/2024Parts area. From north to south 3 to 7 from east to west grid line M to Z.
Okay to backfill progress areas. Shading required.

Canceled per contractor. 10/14/2024
10/16/24: Partial U/G sewer at east side north of the SOI. Ok to backfill progress area.
10/29/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
7/24/24: bedding for sand oil interceptor. Pending test.
8/8/24: plumbing underground per plans from GL S-E/7-3 ok to backfill

9/10/2024Parts area. From north to south 3 to 7 from east to west grid line M to Z.
Okay to backfill progress areas. Shading required.

Canceled per contractor. 10/14/2024
10/16/24: Partial U/G sewer at east side north of the SOI. Ok to backfill progress area.
10/29/24: oil/water separator installed and under test ok to proceed.
10/31/2024 COT - HCPL - Sewer  Partial Pass 10/31/2024 Z line at eye wash. 15.5-12 line of the shop. Rest of tie in underground. Okay to backfill progress areas.
11/07/2024 COT - HCPL - Sewer  Partial Pass 4/22/24: 60' of 6' PVC piping from Manhole #1 to cleanout#1 ok to backfill.
4/24/24: From Clean out #1 to Clean out #2 ok to backfill.
4/26/24: From clean out #3 to Clean out #4 ok to backfill.
4/30/24: Ok to backfill from cleanout #1 to cleanout #6
5/6/24 partial approval for 7 through 10
5/8/24: sewer under pressure at 5psi for 15min. Passed.
7/24/24: bedding for sand oil interceptor. Pending test.
8/8/24: plumbing underground per plans from GL S-E/7-3 ok to backfill

9/10/2024Parts area. From north to south 3 to 7 from east to west grid line M to Z.
Okay to backfill progress areas. Shading required.

Canceled per contractor. 10/14/2024
10/16/24: Partial U/G sewer at east side north of the SOI. Ok to backfill progress area.
10/29/24: oil/water separator installed and under test ok to proceed.

10/31/2024 Z line at eye wash. 15.5-12 line of the shop. Rest of tie in underground. Okay to backfill progress areas.
11/7/24: Partial U/G Sewer at east side Hangar