Inspection Status: Partial Pass
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 11/03/2026 |
COT - LCBU - Framing |
|
Partial Pass |
11/3/26: partial pass pending RFI approval on 3 5/8" studs change at south entrance door and in fill at roll up doors. Okay to continue with TI at progress areas. Use framing inspection to schedule a drywall screw inspection. |
| 11/16/2026 |
COT - LCBU - Framing |
|
Not Ready |
11/16/2026 screws shall not be within 3/8" from all edges. Screws over penetrated throughout. Missing screws at bottom perimeters. Not ready. |