Inspection Status: Canceled
Inspection History: COT - LCBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2026 | COT - LCBU - Preslab | Canceled | 9/25/26: canceled. | |
| 10/22/2026 | COT - LCBU - Preslab | Partial Pass | 10/22/26: reinforcement/excavation on 25 interior Isolated Footings verified per footing schedule on page S004. G/L: 2/B,C,D,E, F. 3/B,C,D,E,F. A/B,C,D,E,F. 5/B,C,D,E, F. 6/B,C,D,E,F. Okay for concrete placement at progress areas. | |
| 11/13/2026 | COT - LCBU - Preslab | Partial Pass | 11/13/26: pre slab, excavation/reinforcement layout at far east slab on grade, dock walls & footings verified per detail 107, 105, 102, 103. Okay for concrete placement. Note: provide clarification on whether dowels to existing concrete at building are required. If so, submit an RFI for review & approval. |
|
| 11/16/2026 | COT - LCBU - Preslab | Partial Pass | 11/16/26: verified dry pack on 10 columns at far east slab together with #5 dowels spaced at 24" o.c. Into the north side of the existing building. | |
| 11/18/2026 | COT - LCBU - Preslab | Partial Pass | 11/18/26: inspected center slab on grade together with 10 grouted columns & reinforcement/dowels verified per detail 101. Okay for concrete placement. |