Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 01/07/2026 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
1-7-26: reschedule pour back when dowels are in place. |
| 01/16/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
1-16-26: in wall DWV/ domestic verified under test. Okay to continue with TI at progress areas. |
| 02/18/2026 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
2-18-26: gas pressure test previously approved. However, contractor placed the whole system under test at 5 psi-okay for SWG to install new meter. Clearance issued. |
| 03/09/2026 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
3-9-26: plumbing intermediate approved. |