Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: TC-COM-0625-01179

Parcel: 140122150


Addresses:

5005 S CAMPBELL AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Rough Soil 

Date Description Inspector Results Comments
01/05/2026 COT - HCPL - Rough Soil  Partial Pass 1/6/25: All rough plumbing approved. Revision will be submitted for review. Ok to backfill at risk.
01/08/2026 COT - HCPL - Rough Soil  Partial Pass 8-26: reinforcement for pour back at underground DWV areas approved. Plans called for #3 & 32" o.c. but contractor used 5/8" & 32" o.c... Okay for concrete placement at progress areas.
01/16/2026 COT - HCPL - Rough Soil  Passed 1-16-26: approved.