Permit: TC-COM-0624-01275

Parcel: 14139001A


Addresses:

9210 E VALENCIA RD

Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
02/11/2025 COT - HCEL - Electrical Underground  Partial Pass 2/11/25: Electrical and Plumbing underground at slab passed ok to proceed.
03/03/2025 COT - HCEL - Electrical Underground  Partial Pass 2/11/25: Electrical and Plumbing underground at slab passed ok to proceed.
3/3/25: electrical underground from existing transformer location to south end of building at new transformer location. Ok to backfill progress areas.
03/06/2025 COT - HCEL - Electrical Underground  Re-inspection required 3-6-25, no approved set of plans for 4- 4" conduits for new transformer. Attempted to contact Chris but got no answer 1116am.
05/01/2025 COT - HCEL - Electrical Underground  Partial Pass 2/11/25: Electrical and Plumbing underground at slab passed ok to proceed.
3/3/25: electrical underground from existing transformer location to south end of building at new transformer location. Ok to backfill progress areas.
3-6-25, no approved set of plans for 4- 4" conduits for new transformer. Attempted to contact Chris but got no answer 1116am.
5/1/25: partial pass for exterior electrical underground for light poles on north half of site approved.
05/02/2025 COT - HCEL - Electrical Underground  Partial Pass 2/11/25: Electrical and Plumbing underground at slab passed ok to proceed.
3/3/25: electrical underground from existing transformer location to south end of building at new transformer location. Ok to backfill progress areas.
3-6-25, no approved set of plans for 4- 4" conduits for new transformer. Attempted to contact Chris but got no answer 1116am.
5/1/25: partial pass for exterior electrical underground for light poles on north half of site approved.
5/2/25:partial pass for exterior electrical underground for light poles on south half of site approved.
09/10/2025 COT - HCEL - Electrical Underground  Passed