Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
Permit Number - TC-COM-0624-01147
Inspection Description - COT - HCEL - Electrical Underground
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. | |
| 04/30/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. | |
| 05/02/2025 | COT - HCEL - Electrical Underground | Partial Pass | 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'. | |
| 05/06/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 |
|
| 05/08/2025 | COT - HCEL - Electrical Underground | Partial Pass | 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. | |
| 05/12/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. |
|
| 05/19/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. 5/19/25: Electrical underground per plans from Electrical room 131 to Electrical room 150 (1) 1 1/4" Schedule 40 pvc and (2) 1" schedule 40 pvc. |
|
| 05/21/2025 | COT - HCEL - Electrical Underground | Partial Pass | Electric conduits (1 1/2” - 3”) at Southeast distribution area. Approximately 50 feet, Ok to cover progress areas. | |
| 05/22/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. 5/19/25: Electrical underground per plans from Electrical room 131 to Electrical room 150 (1) 1 1/4" Schedule 40 pvc and (2) 1" schedule 40 pvc. 5/22/25: Electrical underground in room 141 (6)-1” (6)-2” |
|
| 06/02/2025 | COT - HCEL - Electrical Underground | Partial Pass | Southeast area, IDF Room. Ok to place concrete for underground conduits. | |
| 06/23/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. 5/19/25: Electrical underground per plans from Electrical room 131 to Electrical room 150 (1) 1 1/4" Schedule 40 pvc and (2) 1" schedule 40 pvc. 5/22/25: Electrical underground in room 141 (6)-1” (6)-2” 6/23/25: electrical underground per plans from GL A/2-6, GL A-D/2, GL E/1-3 |
|
| 07/08/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. 5/19/25: Electrical underground per plans from Electrical room 131 to Electrical room 150 (1) 1 1/4" Schedule 40 pvc and (2) 1" schedule 40 pvc. 5/22/25: Electrical underground in room 141 (6)-1” (6)-2” 6/23/25: electrical underground per plans from GL A/2-6, GL A-D/2, GL E/1-3 7/8/25: electrical underground per plan at slab. Pending GL A/1-10 |
|
| 07/21/2025 | COT - HCEL - Electrical Underground | Partial Pass | Southwest area: 12 each 1” conduits for,under slab power. | |
| 07/28/2025 | COT - HCEL - Electrical Underground | Partial Pass | Conduits at 3/4” - 1” in areas 6A - 6C, 8C - 8E, 10E. OK to cover progress areas. | |
| 08/15/2025 | COT - HCEL - Electrical Underground | Partial Pass | 8-15-25: verified under slab secondary 3/4"-2" electrical conduits from gridline C-E/4-7 & A-C/0.1-0.4. Okay to continue with construction at progress areas. | |
| 08/18/2025 | COT - HCEL - Electrical Underground | Partial Pass | 4-29-25, verified depth for approximately 70' of Schedule 40 electrical conduits located on southeast section of site. Okay to backfill progress area. 4-30-25, approximately 170' of electrical Schedule 40 conduits consisting of 2" & 1 1/4" verified per plans. Okay to backfill and continue with construction at progress areas. 5-2-25, verified depth for 5- 1"and 3-2" electrical Schedule 40 conduits. Okay to backfill progress areas of approximately 60'.' 5/6/25: approximately 200' of electrical conduit (3) 2" and (1) 1" to IT room# 115 5-8-25, verified depth on approximately 50' of Schedule 40 conduits from IT room#141-carts room #102. Okay to backfill progress areas. 5/12/25: partial pass for UFER. 5/19/25: Electrical underground per plans from Electrical room 131 to Electrical room 150 (1) 1 1/4" Schedule 40 pvc and (2) 1" schedule 40 pvc. 5/22/25: Electrical underground in room 141 (6)-1” (6)-2” 6/23/25: electrical underground per plans from GL A/2-6, GL A-D/2, GL E/1-3 7/8/25: electrical underground per plan at slab. Pending GL A/1-10 8-15-25: verified under slab secondary 3/4"-2" electrical conduits from gridline C-E/4-7 & A-C/0.1-0.4. Okay to continue with construction at progress areas. 8/18/25: electrical in slab at areas C-D approved ok to proceed. |
|
| 08/22/2025 | COT - HCEL - Electrical Underground | Partial Pass | Electric conduits at 3/4” - 1” in Yellow section at GL: 2.9 - 0.2/B - G. Ok to place concrete in progress areas. | |
| 09/29/2025 | COT - HCEL - Electrical Underground | Partial Pass | Grid line 2.9 - 4.1. Columns B1 - G. Floor boxes. Grid line 1 - 2.9. Columns G.3 - F. Floor boxes. 9/29/2025 |
|
| 10/06/2025 | COT - HCEL - Electrical Underground | Partial Pass | 10-6-25: verified trench depth for several 3" schedule 40 primary conduits located on the southeastern section of building. Okay to backfill progress areas. | |
| 10/07/2025 | COT - HCEL - Electrical Underground | Partial Pass | Conduit lines from Southeast portion of building to area to be forwarded to new transformer (conduits at 1’ - 3”); approximately 55 feet of trenching. | |
| 10/10/2025 | COT - HCEL - Electrical Underground | Not Ready | ||
| 10/16/2025 | COT - HCEL - Electrical Underground | Partial Pass | 10-16-25: verified trench depth for several electrical primary Schedule 40 conduits ranging from 1 1/2" to 4" from generator to SES/CT located at the south-southeast side of building. Okay to backfill approximately 30' of trench. | |
| 10/21/2025 | COT - HCEL - Electrical Underground | Partial Pass | 10-21-25: electrical underground of main feeders consisting of 4-4" & 1-1 1/2" Schedule 40 conduits located on the southeast section of site. Okay to backfill trench of approximately 130' with shading materials. | |
| 10/23/2025 | COT - HCEL - Electrical Underground | Partial Pass | 10-23-25: verified trench depth on 4-4" and 1 1/2" schedule 40 conduits to transformer. Okay to backfill 40' of trench. |