Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0624-01147

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, excavation/reinforcement for 14 column spread footers on south end verified per plan. Detail F-6 calls for 7-#5 rebar top/bottom and F-8-calls for 9-#6 rebar top/bottom. Okay to pour footers at progress areas.
04/30/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-30-25, excavation/reinforcement on a total of 18 interior spread footings verified per approved plans.See Detail's F-6 & F4.5, F3X6. Okay to pour concrete.
05/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5-2-25, excavation/reinforcement on a total of 33 spread footings verified per approved plans-see detail F-4, F-6, F-8. Okay to pour concrete.
05/12/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, excavation/reinforcement for 14 column spread footers on south end verified per plan. Detail F-6 calls for 7-#5 rebar top/bottom and F-8-calls for 9-#6 rebar top/bottom. Okay to pour footers at progress areas.
4-30-25, excavation/reinforcement on a total of 18 interior spread footings verified per approved plans.See Detail's F-6 & F4.5, F3X6. Okay to pour concrete.
5-2-25, excavation/reinforcement on a total of 33 spread footings verified per approved plans-see detail F-4, F-6, F-8. Okay to pour concrete.
5/12/25: reinforcement per plans at exterior continuous perimeter footer at GL (A/0-10, A-D/11). Ok to proceed with progress areas.
05/16/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, excavation/reinforcement for 14 column spread footers on south end verified per plan. Detail F-6 calls for 7-#5 rebar top/bottom and F-8-calls for 9-#6 rebar top/bottom. Okay to pour footers at progress areas.
4-30-25, excavation/reinforcement on a total of 18 interior spread footings verified per approved plans.See Detail's F-6 & F4.5, F3X6. Okay to pour concrete.
5-2-25, excavation/reinforcement on a total of 33 spread footings verified per approved plans-see detail F-4, F-6, F-8. Okay to pour concrete.
5/12/25: reinforcement per plans at exterior continuous perimeter footer at GL (A/0-10, A-D/11). Ok to proceed with progress areas.
5/16/25: reinforcement per approved plans at continuous perimeter panel footings from GL A-G.5/2-2
05/19/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, excavation/reinforcement for 14 column spread footers on south end verified per plan. Detail F-6 calls for 7-#5 rebar top/bottom and F-8-calls for 9-#6 rebar top/bottom. Okay to pour footers at progress areas.
4-30-25, excavation/reinforcement on a total of 18 interior spread footings verified per approved plans.See Detail's F-6 & F4.5, F3X6. Okay to pour concrete.
5-2-25, excavation/reinforcement on a total of 33 spread footings verified per approved plans-see detail F-4, F-6, F-8. Okay to pour concrete.
5/12/25: reinforcement per plans at exterior continuous perimeter footer at GL (A/0-10, A-D/11). Ok to proceed with progress areas.
5/16/25: reinforcement per approved plans at continuous perimeter panel footings from GL A-G.5/2-2
5/19/25: perimeter panel footings at south/west/east exterior walls reinforced per plan ok to proceed.
05/21/2025 COT - HCBU - Excavation/Rebar/Zoning  Canceled Contractor cancelled.
05/22/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-29-25, excavation/reinforcement for 14 column spread footers on south end verified per plan. Detail F-6 calls for 7-#5 rebar top/bottom and F-8-calls for 9-#6 rebar top/bottom. Okay to pour footers at progress areas.
4-30-25, excavation/reinforcement on a total of 18 interior spread footings verified per approved plans.See Detail's F-6 & F4.5, F3X6. Okay to pour concrete.
5-2-25, excavation/reinforcement on a total of 33 spread footings verified per approved plans-see detail F-4, F-6, F-8. Okay to pour concrete.
5/12/25: reinforcement per plans at exterior continuous perimeter footer at GL (A/0-10, A-D/11). Ok to proceed with progress areas.
5/16/25: reinforcement per approved plans at continuous perimeter panel footings from GL A-G.5/2-2
5/19/25: perimeter panel footings at south/west/east exterior walls reinforced per plan ok to proceed.
5/22/25: perimeter footings at North exterior walls reinforced per plans at GL E.5-H/0.1-9
06/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Tilt Panels #4 - 19. Ok to place concrete in progress areas.
06/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Total of 3 exterior column footing detail 5 page S2.1. Okay for concrete placement. 6/3/2025
06/06/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1 exterior column footings detail 5 page S2.1.
2 grade beams and spread footers approved. Reinforcements per plan. Okay for concrete placement. 6/6/2025
06/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Tilt up panels 36-69 approved. Reinforcements and clearances per plan okay for concrete placement. 6/10/2025
09/04/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/4/25: reinforcement approved at fish tank pad/footer
09/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9-11-25: reinforcement at aquarium verified per plans. Okay for concrete placement at progress areas.
10/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 10-3-25: not ready-arrived on site at 1300 hours and made contact with contractor. Inspection is for slab on grade but wasn't ready. Contractor may consider same day inspection.
10/05/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10-6-25: reinforcement for slab on grade verified per plans. Okay for concrete placement between Gridlines 2-2.8 to 4.1/ C-F.