Inspection Status: Not Ready
Inspection History: COT - HCBU - TCO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2026 | COT - HCBU - TCO | Not Ready | ||
| 02/05/2026 | COT - HCBU - TCO | Re-inspection required | Inspection Findings – 2/5/26 During a site visit on February 5, 2026, the following observations were made regarding the Bass Pro project: 1. Building Condition: Shelving, racking systems, furniture, and electronics have been laid out throughout the premises without approval of a TCO Level 1. 2. Life Safety Concerns: o Open electrical boxes, obstructed egress routes, emergency lighting, and panel schedules are not complete. o All life safety items must be addressed prior to issuance of a Level 1 TCO. 3. Personnel on Site: Bass Pro employees were present on-site and were not wearing appropriate PPE for a construction environment. 4. TCO Requirements: o A Level 2 TCO would be required to allow for staffing and training. o The current state of construction does not comply with City of Tucson requirements for issuance of a Level 1 or Level 2 TCO. 5. Separation of Construction and Occupied Areas: o There is no separation between the construction site and employee areas. o Separation must be provided and documented prior to TCO approval. 6. Construction and Egress Requirements: o All construction equipment must be removed from the building. o Egress routes must be accessible and properly landed. o Egress must be provided for all exit doors. o A site plan and egress plan are required prior to approval to document separation and access. 7. Parking: The parking lot is incomplete; designated parking spaces are required prior to Level 2 TCO approval, 8. Approvals Required: Final approval of a Level 2 TCO requires sign-off from the Fire Marshal, Engineering, and Building Inspections. |
|
| 02/09/2026 | COT - HCBU - TCO | Partial Pass | 2/9/26: OKAY FOR LEVEL 2 TCO | |
| 03/25/2026 | COT - HCBU - TCO | Partial Pass | 3/25/2026: Approval is granted for Level 3 TCO for the sales floor and employee-only restrooms. This approval does not include the coffee shop/snack area and excludes customer restrooms. Temporary restroom facilities must be provided for customers, including at least one ADA-accessible restroom with appropriate handwashing stations. | |
| 03/27/2026 | COT - HCBU - TCO | Partial Pass | 3/27/26:Approval is granted for Level 4 TCO .This approval does not include the coffee shop/snack area. | |
| 04/01/2026 | COT - HCBU - TCO | Re-inspection required | ||
| 04/03/2026 | COT - HCBU - TCO | Partial Pass | 4/3/26: Approval is granted for LEVEL 4 TCO. This approval includes the coffee shop/snack area. Please ensure to apply for Level 4 TCO. |