Inspection Status: Not Ready

Inspection History: COT - HCBU - TCO

Date Description Inspector Results Comments
02/05/2026 COT - HCBU - TCO Not Ready
02/05/2026 COT - HCBU - TCO Re-inspection required Inspection Findings – 2/5/26
During a site visit on February 5, 2026, the following observations were made regarding the Bass Pro project:
1. Building Condition: Shelving, racking systems, furniture, and electronics have been laid out throughout the premises without approval of a TCO Level 1.
2. Life Safety Concerns:
o Open electrical boxes, obstructed egress routes, emergency lighting, and panel schedules are not complete.
o All life safety items must be addressed prior to issuance of a Level 1 TCO.
3. Personnel on Site: Bass Pro employees were present on-site and were not wearing appropriate PPE for a construction environment.
4. TCO Requirements:
o A Level 2 TCO would be required to allow for staffing and training.
o The current state of construction does not comply with City of Tucson requirements for issuance of a Level 1 or Level 2 TCO.
5. Separation of Construction and Occupied Areas:
o There is no separation between the construction site and employee areas.
o Separation must be provided and documented prior to TCO approval.
6. Construction and Egress Requirements:
o All construction equipment must be removed from the building.
o Egress routes must be accessible and properly landed.
o Egress must be provided for all exit doors.
o A site plan and egress plan are required prior to approval to document separation and access.
7. Parking: The parking lot is incomplete; designated parking spaces are required prior to Level 2 TCO approval,
8. Approvals Required: Final approval of a Level 2 TCO requires sign-off from the Fire Marshal, Engineering, and Building Inspections.
02/09/2026 COT - HCBU - TCO Partial Pass 2/9/26: OKAY FOR LEVEL 2 TCO
03/25/2026 COT - HCBU - TCO Partial Pass 3/25/2026: Approval is granted for Level 3 TCO for the sales floor and employee-only restrooms. This approval does not include the coffee shop/snack area and excludes customer restrooms. Temporary restroom facilities must be provided for customers, including at least one ADA-accessible restroom with appropriate handwashing stations.
03/27/2026 COT - HCBU - TCO Partial Pass 3/27/26:Approval is granted for Level 4 TCO .This approval does not include the coffee shop/snack area.
04/01/2026 COT - HCBU - TCO Re-inspection required
04/03/2026 COT - HCBU - TCO Partial Pass 4/3/26: Approval is granted for LEVEL 4 TCO. This approval includes the coffee shop/snack area. Please ensure to apply for Level 4 TCO.