Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Final 

Date Description Inspector Results Comments
03/25/2026 COT - HCBU - Building Final  Partial Pass 3/25/2026: Approval is granted for Level 3 TCO for the sales floor and employee-only restrooms. This approval does not include the coffee shop/snack area and excludes customer restrooms. Temporary restroom facilities must be provided for customers, including at least one ADA-accessible restroom with appropriate handwashing stations.
08/10/2026 COT - HCBU - Building Final  Partial Pass 8/10/26: Building final partially passed. Pending roof walkthrough (HVAC equipment, supports on gas piping, vents , Pending mini split for food court, pending Engineering final, pending Fire finals, Pending ROW, Pending Building Finals (Electrical,Mechanical,Plumbing), Pending conditions.