Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2024 | COT - HCEL - Electrical Progress | Partial Pass | 1/29/24: electrical rough-in in-wall rooms 103,102,101,110,108,105,106,109,108 ok to one side, warehouse west wall ok to cover up and proceed. | |
| 03/18/2024 | COT - HCEL - Electrical Progress | Partial Pass | 1/29/24: electrical rough-in in-wall rooms 103,102,101,110,108,105,106,109,108 ok to one side, warehouse west wall ok to cover up and proceed. 3/18/24: electrical above ceiling in rooms 103,102,101,110,108,105,106,109,108 ok to proceed. |
|
| 06/11/2024 | COT - HCEL - Electrical Progress | Partial Pass | 1/29/24: electrical rough-in in-wall rooms 103,102,101,110,108,105,106,109,108 ok to one side, warehouse west wall ok to cover up and proceed. 3/18/24: electrical above ceiling in rooms 103,102,101,110,108,105,106,109,108 ok to proceed. 6/11/24: electrical underground for relocation of panel GSEC and data cabinet. (2) 2" from current location to 100' south west to new location for panel and (3) 2" for data. |
|
| 06/17/2024 | COT - HCEL - Electrical Progress | Partial Pass | 1/29/24: electrical rough-in in-wall rooms 103,102,101,110,108,105,106,109,108 ok to one side, warehouse west wall ok to cover up and proceed. 3/18/24: electrical above ceiling in rooms 103,102,101,110,108,105,106,109,108 ok to proceed. 6/11/24: electrical underground for relocation of panel GSEC and data cabinet. (2) 2" from current location to 100' south west to new location for panel and (3) 2" for data. 6/17/24: ok to backfill relocation of gate control panel and data cabinet. On east side of building |
|
| 07/10/2024 | COT - HCEL - Electrical Progress | Passed |