Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
Permit Number - TC-COM-0623-01485
Inspection Description - COT - HCPL - Plumbing Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/26/2024 | COT - HCPL - Plumbing Progress | Partial Pass | Not ready. Correct S TRAP at floor drain. Re pressurize system. 11/13/2023 11/15/23: corrections made ok to backfill underground plumbing in bldg G. 12/21/23 plumbing under slab ok to backfill, from floor drains to main sewer tap outside roof up door on loading dock 1/26/24: DWV from mechanical room 10 to mens and women's restroom per plan and under Test. Ok to proceed. Hot and cold water lines per plan and under pressure at 100psi. Cold water tied into main. Hot water connections tapped off and will be connected to water heater. |
|
03/18/2024 | COT - HCPL - Plumbing Progress | Partial Pass | Not ready. Correct S TRAP at floor drain. Re pressurize system. 11/13/2023 11/15/23: corrections made ok to backfill underground plumbing in bldg G. 12/21/23 plumbing under slab ok to backfill, from floor drains to main sewer tap outside roof up door on loading dock 1/26/24: DWV from mechanical room 10 to mens and women's restroom per plan and under Test. Ok to proceed. Hot and cold water lines per plan and under pressure at 100psi. Cold water tied into main. Hot water connections tapped off and will be connected to water heater. 3/18/24: plumbing above ceiling approved in rooms 103,102,101,110,108,105,106,109,108 ok to proceed. |
|
05/15/2024 | COT - HCPL - Plumbing Progress | Partial Pass | Not ready. Correct S TRAP at floor drain. Re pressurize system. 11/13/2023 11/15/23: corrections made ok to backfill underground plumbing in bldg G. 12/21/23 plumbing under slab ok to backfill, from floor drains to main sewer tap outside roof up door on loading dock 1/26/24: DWV from mechanical room 10 to mens and women's restroom per plan and under Test. Ok to proceed. Hot and cold water lines per plan and under pressure at 100psi. Cold water tied into main. Hot water connections tapped off and will be connected to water heater. 3/18/24: plumbing above ceiling approved in rooms 103,102,101,110,108,105,106,109,108 ok to proceed. 5/15/24: underground plumbing at east half of building per plans ok to proceed. |
|
07/10/2024 | COT - HCPL - Plumbing Progress | Passed | ||
11/13/2023 | COT - HCPL - Plumbing Progress | Re-inspection required | Not ready. Correct S TRAP at floor drain. Re pressurize system. 11/13/2023 | |
11/15/2023 | COT - HCPL - Plumbing Progress | Partial Pass | Not ready. Correct S TRAP at floor drain. Re pressurize system. 11/13/2023 11/15/23: corrections made ok to backfill underground plumbing in bldg G. |
|
12/21/2023 | COT - HCPL - Plumbing Progress | Partial Pass | 12/21/23 plumbing under slab ok to backfill, from floor drains to main sewer tap outside roof up door on loading dock |