Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 05/23/2024 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial pass. Phase 1 (North portion of lot). X2 1" & 3/4" conduits schedule 40 pvc going to the furthest island. X2 1" & 3/4" going to middle island. X2 1" & 3/4" going to Inter grade island. X2 1" conduit going to canopy base plate at first island and to pay kiosk. X3 1 1/2" conduit for bug juice at canopy base plate. Primary for utility transformer 4" schedule 40 at 40" depth to pole box. Okay to backfill progress areas. Shading is required. 5/23/2024 |
| 06/28/2024 |
COT - LCEL - Electrical Underground |
|
Passed |
6/28/24 - all conduits to pay stations complete. 4" conduits from transformer to ct can at existing car wash complete. Conduits to vacuum stations 1 and 2 complete. Note: vacuum station 1 footing ok to pour. Dozens of other 3/4" and 1" distribution conduits complete and ready to backfill. 2" and 3" conduits to pull gutter uninstructed frame, ok to backfill. All site underground electric complete and ok to backfill. |