Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 01/10/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial for the riser at canopy A, okay for concrete placement progress areas |
| 01/12/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
1/12/24 electrical underground canopy B ok to backfill |
| 01/23/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Canceled |
Canceled by Jerry at 7:45 |
| 01/24/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial approval. For canopy A and B. bore holes. Okay to backfill. Shading required. 1/24/24 |
| 02/01/2024 |
COT - CSOL - Electrical Underground Solar Project |
|
Passed |
Approved and complete underground from bore pits to panel/equipment, okay to for concrete placement |