Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2026 | COT - LCBU - Building Final | Not Ready | ||
| 08/03/2026 | COT - LCBU - Building Final | Not Ready | Building 6. Unit 112. Remove door were sub panel is n place. Provide new sub panel due to paint inside. Laundry room. Provide ko seals at all knock outs at j boxes. Provide GFCI protection at all receptacles in laundry room. Remove all screws from dryer ducts. Provide supports at line sets in mechanical room. Secure mc cable. Re secure flue collar. Provide individual pressure relief valve at water heaters. S trap at sink. 114 Provide anti tip at range. Remove door at closet with sub panel. |
|
| 08/18/2026 | COT - LCBU - Building Final | Partial Pass | 8/18/2026 Partial pass. Okay to apply for level 4 TCO for all units. pending for the corrections to be made for the type 1r electrical panels. |