Inspection Status: Passed
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 07/17/2026 |
COT - HCBU - Framing |
|
Passed |
7-17-26: framing inspection approved. |
| 10/15/2026 |
COT - HCBU - Framing |
|
Re-inspection required |
10/15/26: have architect of record provide a letter to the city documenting RC Channels- spacing and type of screws. Plywood screws for lighting wells approved. |
| 10/23/2026 |
COT - HCBU - Framing |
|
Partial Pass |
10/23/26: RC channels approved. Okay to drywall but schedule a drywall screw inspection prior to tape & texture. |
| 11/04/2026 |
COT - HCBU - Framing |
|
Partial Pass |
11/4/26: verified A34's, H3's, LTS12's and blocking for additional supports at light boxes. RFI to be submitted to the city for review-I uploaded the detail as an attachment on IG Inspect. Okay to drywall light boxes at own risk but schedule a drywall screw inspection prior to tape & texture. |
| 11/06/2026 |
COT - HCBU - Framing |
|
Partial Pass |
11/6/26: drywall screw inspection approved. Okay to tape & texture. |