Permit: TC-COM-0526-00653

Parcel: 14118658A


Addresses:

10084 E OLD VAIL RD

Inspection Status: Partial Pass

Inspection History: COT - LCBU - Masonry Pregrout 

Date Description Inspector Results Comments
COT - LCBU - Masonry Pregrout  Partial Pass 10/14/26: reinforcement for CMU stem walls at 4' west wall, north wall at G/L: 10-6/ A at 44" East stem wall at 12", 2' at south wall. Reinforcement verified per details 108, 124, 110B, 110C, 109, 103, wall footing schedule on S1.4 & remaining details on S3.1. Okay for concrete placement at progress areas.
10/15/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/15.26: G/L: A/1-6 at 5'-okay to grout at own risk. City allows 4' maximum lifts- Building official approval is required for anything above 4'. Also, blow outs will be required at 4' intervals. Obtain approval prior to continuing with lifts taller than 4'.
10/16/2026 COT - LCBU - Masonry Pregrout  Canceled 10/16/26: canceled by contractor.
10/19/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/19/26 partial pass first lift S, E, and N, as well as steam and equipment rooms
10/21/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/21/26: reinforcement at cmu walls at G/L: 10/B-H-2nd lift at 8' & G/L:1 & 5/G-J-2nd lift at 8' verified per plans. Okay to grout.
10/22/2026 COT - LCBU - Masonry Pregrout  Partial Pass Grid line 10, 3rd lift.
10/22/2026 COT - LCBU - Masonry Pregrout  Partial Pass North wall, 3rd lift.
10/23/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/23/26
Grid line J1-6; A1-J1
10/27/2026 COT - LCBU - Masonry Pregrout  Partial Pass
10/29/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/29/26
Pre-grout south wall and, Grid line J10-L.
10/30/2026 COT - LCBU - Masonry Pregrout  Partial Pass 10/30/26
South wall; west walls
11/03/2026 COT - LCBU - Masonry Pregrout  Partial Pass 11.3.26
Next lift south wall, partial east, and west wall.
11/04/2026 COT - LCBU - Masonry Pregrout  Partial Pass 11.4.26
Top out north wall, and top out on west wall A1-D.
COT - LCBU - Masonry Pregrout  Scheduled