Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Masonry Pregrout
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - LCBU - Masonry Pregrout | Partial Pass | 10/14/26: reinforcement for CMU stem walls at 4' west wall, north wall at G/L: 10-6/ A at 44" East stem wall at 12", 2' at south wall. Reinforcement verified per details 108, 124, 110B, 110C, 109, 103, wall footing schedule on S1.4 & remaining details on S3.1. Okay for concrete placement at progress areas. | ||
| 10/15/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/15.26: G/L: A/1-6 at 5'-okay to grout at own risk. City allows 4' maximum lifts- Building official approval is required for anything above 4'. Also, blow outs will be required at 4' intervals. Obtain approval prior to continuing with lifts taller than 4'. | |
| 10/16/2026 | COT - LCBU - Masonry Pregrout | Canceled | 10/16/26: canceled by contractor. | |
| 10/19/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/19/26 partial pass first lift S, E, and N, as well as steam and equipment rooms | |
| 10/21/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/21/26: reinforcement at cmu walls at G/L: 10/B-H-2nd lift at 8' & G/L:1 & 5/G-J-2nd lift at 8' verified per plans. Okay to grout. | |
| 10/22/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | Grid line 10, 3rd lift. | |
| 10/22/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | North wall, 3rd lift. | |
| 10/23/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/23/26 Grid line J1-6; A1-J1 |
|
| 10/27/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | ||
| 10/29/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/29/26 Pre-grout south wall and, Grid line J10-L. |
|
| 10/30/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 10/30/26 South wall; west walls |
|
| 11/03/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 11.3.26 Next lift south wall, partial east, and west wall. |
|
| 11/04/2026 | COT - LCBU - Masonry Pregrout | Partial Pass | 11.4.26 Top out north wall, and top out on west wall A1-D. |
|
| COT - LCBU - Masonry Pregrout | Scheduled |