| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2026 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 9/24/26: Section by grid line A and 10 All grids line A All follow the 121 detail Grid line A on the West side Detail 123 Grid line 1 A-D Detail 102 Rebar conditions 110A 110B 109 110B 109 110A |
|
| 10/08/2026 | COT - LCBU - Excavation/Rebar/Zoning | Partial Pass | 10.8.26 J/h line 9 requires RFI submittal for approval of configuration Inspected all 12 Interior footers meet listed detail requirements but must be cleaned of debris and obstructions Exterior footings inspected D10 to d6 (southeastcorner ) Ok for concrete placement at progress areas |
|
| 10/09/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed |