Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 03/02/2026 |
COT - HCBU - Framing |
|
Partial Pass |
This inspection is for pre-slab at Level #1; North half of basement area. Ok to place concrete in progress areas. |
| 09/25/2025 |
COT - HCBU - Framing |
|
Partial Pass |
This inspection is for excavation/layout and rebar: Elevator pad at GL: A.5-B.5/1.5-2. Column footing (F7) at GL: C/1.8. OK to place concrete in progress areas. |
| 10/01/2025 |
COT - HCBU - Framing |
|
Not Ready |
|