Inspection Status: Not Ready
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - HCEL - Electrical Intermediate |
|
Not Ready |
9/18/24: needed electrical underground |
| 02/21/2025 |
COT - HCEL - Electrical Intermediate |
|
Passed |
2/21/25: Transformer is being set in interior electrical room, panels for lighting and receptacles are being trimmed out. New main panel and disconnects are installed. Okay to proceed with further work. |
| 10/25/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
10/25/24: Electrical rough-in is complete on all framed walls and above ceiling. Sub-panels are being installed in electrical room. |
| 11/12/2024 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
11-12-24, above ceiling insulation on mechanical inspected and approved. Above ceiling electrical verified per approved plans. Okay to continue construction. |