Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/23/2024 |
ENGR Engineering Final
|
|
Not Ready |
Spoke with Victor Gonzales and we did thee pre-construction meeting for the new concrete pass thru area located at the North end center of parking lot between building (12) & (21) Victor will recall inspection when ab and compaction test are completed to have curb, gutter, and rebar inspected. |
| 05/03/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Ramp at north end |
| 10/29/2024 |
ENGR Engineering Final
|
|
Passed |
|