Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Building Progress
Permit Number - TC-COM-0523-01319
Inspection Description - COT - LCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2024 | COT - LCBU - Building Progress | Partial Pass | Partial pass electrical in wall at both exterior stairs okay to proceed progress areas. 2/20/2024 | |
| 02/26/2024 | COT - LCBU - Building Progress | Partial Pass | ||
| 03/07/2024 | COT - LCBU - Building Progress | Partial Pass | #202, #200, and #203 building 6. 2032 e River. Drywall approved. Pending other units. 3/7/2024 | |
| 03/14/2024 | COT - LCBU - Building Progress | Partial Pass | 3/14/24: units #201,204,205 okay to mud and tape. | |
| 03/20/2024 | COT - LCBU - Building Progress | Not Ready | 3/20/2024 drywall nailing not ready for lower units. | |
| 03/21/2024 | COT - LCBU - Building Progress | Canceled | Canceled per contractor. 3/21/2024 | |
| 03/22/2024 | COT - LCBU - Building Progress | Partial Pass | 3/22/24: 100, 101,102,103 okay to mud and tape walls waiting for intermediate mechanical before covering of ceiling | |
| 03/28/2024 | COT - LCBU - Building Progress | Canceled | Canceled per contractor. 3/28/2024 | |
| 04/02/2024 | COT - LCBU - Building Progress | Partial Pass | Partial pass units 104 and 105. Drywall inspection. Pending lids at soffit areas. 4/2/2024 | |
| 04/05/2024 | COT - LCBU - Building Progress | Not Ready | ||
| 04/08/2024 | COT - LCBU - Building Progress | Partial Pass | ||
| 07/03/2024 | COT - LCBU - Building Progress | Passed | ||
| 10/13/2023 | COT - LCBU - Building Progress | Not Ready |