Inspection Status: Partial Pass

Inspection History: COT - LCBU - Building Progress

Date Description Inspector Results Comments
02/20/2024 COT - LCBU - Building Progress Partial Pass Partial pass electrical in wall at both exterior stairs okay to proceed progress areas. 2/20/2024
02/26/2024 COT - LCBU - Building Progress Partial Pass
03/07/2024 COT - LCBU - Building Progress Partial Pass #202, #200, and #203 building 6. 2032 e River. Drywall approved. Pending other units. 3/7/2024
03/14/2024 COT - LCBU - Building Progress Partial Pass 3/14/24: units #201,204,205 okay to mud and tape.
03/20/2024 COT - LCBU - Building Progress Not Ready 3/20/2024 drywall nailing not ready for lower units.
03/21/2024 COT - LCBU - Building Progress Canceled Canceled per contractor. 3/21/2024
03/22/2024 COT - LCBU - Building Progress Partial Pass 3/22/24: 100, 101,102,103 okay to mud and tape walls waiting for intermediate mechanical before covering of ceiling
03/28/2024 COT - LCBU - Building Progress Canceled Canceled per contractor. 3/28/2024
04/02/2024 COT - LCBU - Building Progress Partial Pass Partial pass units 104 and 105. Drywall inspection. Pending lids at soffit areas. 4/2/2024
04/05/2024 COT - LCBU - Building Progress Not Ready
04/08/2024 COT - LCBU - Building Progress Partial Pass
07/03/2024 COT - LCBU - Building Progress Passed
10/13/2023 COT - LCBU - Building Progress Not Ready