Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
Permit Number - TC-COM-0523-01171
Inspection Description - ENGR Engineering Final
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/03/2024 | ENGR Engineering Final | Partial Pass | contractor needs to check the slope from the building to the trash enclosure. I checked with my level and it read 8.2% contractor also got put in some gutter off the patio area for the water doesn’t drain onto the sidewalk and the gates on the trash enclosure needs to be hung | |
| 07/10/2024 | ENGR Engineering Final | Partial Pass | i’m giving the contractor TCO4. Contractor still needs to address the roof drain system so the water doesn’t come onto the sidewalk on the west side and one on the north side also has to address the slope from the sidewalk to the trash enclosure cause that exceeds the 5% running slope. | |
| 09/26/2024 | ENGR Engineering Final | Passed |