Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Intermediate Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 07/19/2023 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Partial Pass |
Partial pass. Electrical intermediate interconnection complete. Changed out the power monitor detail 6 on the 1 single line diagram. PNL-01 7/19/2023 |
| 08/02/2023 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Partial Pass |
Partial for all AC components from transformer to panel 1 at canopy, okay to continue |
| 08/11/2023 |
COT - CSOL - Electrical Intermediate Solar Project |
|
Passed |
|