Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
01/05/2026 COT - HCBU - Framing Partial Pass 1-5-26: office framing approved. Okay to continue with construction at progress areas.
01/12/2026 COT - HCBU - Framing Partial Pass 1-12-26: drywall screw inspection at interior side of office together with restroom at warehouse side approved. Okay to tape & texture progress areas.
02/18/2026 COT - HCBU - Framing Not Ready 2-18-26: not ready.
02/25/2026 COT - HCBU - Framing Passed
10/15/2025 COT - HCBU - Framing Partial Pass 10-15-25: framing for demising wall at Unit 2160 of Building 2 verified per details. Okay to One side and schedule a drywall nailing inspection prior to tape & texture.
10/24/2025 COT - HCBU - Framing Partial Pass
11/04/2025 COT - HCBU - Framing Partial Pass 11-4-25: partial pass for suite metal framing- okay to one-side warehouse. Schedule a drywall nailing inspection when ready.