Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
02/23/2026 COT - HCBU - Building Progress Partial Pass Drywall at all interior walls approved. Okay to proceed with tape and mud. 2/23/2026
04/27/2026 COT - HCBU - Building Progress Passed 4-27-26: approved.
11/20/2025 COT - HCBU - Building Progress Canceled 11-20-25: canceled by contractor.
12/05/2025 COT - HCBU - Building Progress Not Ready 12-5-25: not ready.
12/10/2025 COT - HCBU - Building Progress Partial Pass 12/10/2025 Rebar inspection at plumbing trench approved. Okay for concrete placement.
12/18/2025 COT - HCBU - Building Progress Partial Pass 12-18-25: drywall nailing on north side of demising wall approved-okay for tape & texture.
12/29/2025 COT - HCBU - Building Progress Partial Pass 12-29-25: partial pass-missing approximately 40' of drywall at north demising wall. Remainder of north and south demising walls are okay for tape & texture.