Inspection Status: Re-inspection required

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
01/14/2026 COT - HCPL - Plumbing Progress  Re-inspection required 1-14-26: place domestic under test, add 10 mil tape above ceiling where copper is in contact with other metals.
01/15/2026 COT - HCPL - Plumbing Progress  Partial Pass 1-15-26: verified domestic/dwv under test-10 mil tape added. Okay to continue with construction at progress areas
04/27/2026 COT - HCPL - Plumbing Progress  Passed 4-27-26: approved.
11/17/2025 COT - HCPL - Plumbing Progress  Partial Pass 11-17-25: underground plumbing verified per plans. Okay to backfill-shading required.
Note: schedule a dowel & vapor barrier inspection prior to pour back.