Inspection Status: Partial Pass

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
01/13/2026 BULD - Electrical Clearance Partial Pass 01/13/2026
Verbal Clearance TEP RECN at 9:30am. No work completed. Contractor scheduled powerkill to land disconnect wires but not ready since contractor needs to fabricate busbar for a 500 CU line. Contractor is requesting reconnect and partial pass pending solar.
02/10/2026 BULD - Electrical Clearance Partial Pass Verbal clearance to TEP DGL. (Line side tap) 2/10/2026
03/18/2026 BULD - Electrical Clearance Passed DGC
11/13/2025 BULD - Electrical Clearance Not Ready 11.13.2025
Not ready.