Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/02/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Partial approval OK to pour restroom area only please clarify structural drawings on type of floor and whether it's slab on grade or pavers for shed and green greenhouse |
| 05/07/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
|
| 10/25/2024 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Exterior/interior pier footings per plan. Total of 21. Okay for concrete placement. 10/25/2024 |
| 12/10/2024 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Storage Shed/Restroom. Total of 13 footers. Per F1 footing schedule. Okay for concrete placement. 12/10/2024 |