Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/09/2024 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 6/20/24: electrical intermediate passed ok to proceed. Electrical underground passed ok to proceed. Partial pass pending panel fixes, Partial pass pending grills in place. All hard and flex duct throughout elevated and secured. Okay to proceed progress areas. 8/22/2024 9/9/24: properly support flex duct throughout, supply/return registers require seismic wiring, light fixtures require seismic wiring (some have seismic wire cut at fixtures), all j-boxes must be properly covered, knock outs at j-boxes must be sealed. Properly support MC cable, properly support low volt wiring, properly support j-boxes, remove all demo material that no longer will be used, hangers for copper pipe must be coated or taped, insulation required at domestic hot water, all copper piping in contact with dissimilar metals must be protected. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. |
|
| 10/16/2024 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 6/20/24: electrical intermediate passed ok to proceed. Electrical underground passed ok to proceed. Partial pass pending panel fixes, Partial pass pending grills in place. All hard and flex duct throughout elevated and secured. Okay to proceed progress areas. 8/22/2024 9/9/24: properly support flex duct throughout, supply/return registers require seismic wiring, light fixtures require seismic wiring (some have seismic wire cut at fixtures), all j-boxes must be properly covered, knock outs at j-boxes must be sealed. Properly support MC cable, properly support low volt wiring, properly support j-boxes, remove all demo material that no longer will be used, hangers for copper pipe must be coated or taped, insulation required at domestic hot water, all copper piping in contact with dissimilar metals must be protected. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. 9/9/24: properly support flex duct throughout, supply/return registers require seismic wiring, light fixtures require seismic wiring (some have seismic wire cut at fixtures), all j-boxes must be properly covered, knock outs at j-boxes must be sealed. Properly support MC cable, properly support low volt wiring, properly support j-boxes, remove all demo material that no longer will be used, hangers for copper pipe must be coated or taped, insulation required at domestic hot water, all copper piping in contact with dissimilar metals must be protected. STOPPED INSPECTION MORE ITEMS MAY BE ADDED. 10/16/24: corrections pending per previous notes. All ceiling tiles have been installed, please remove ceiling tiles in order to conduct proper inspection. Air balance report required, water sterilization report required |
|
| 10/24/2024 | COT - HCEL - Electrical Above Ceiling | Passed | 10/24/2024 approved. |