Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2024 | COT - HCBU - Preslab | Partial Pass | 3/4/24: footing reinforcement per plan at GL A-F/1-7 | |
| 03/28/2024 | COT - HCBU - Preslab | Partial Pass | 3/4/24: footing reinforcement per plan at GL A-F/1-7 3/28/24: Preslab at building ok to pour. |
|
| 05/29/2024 | COT - HCBU - Preslab | Not Ready | Pending other footings such as menu footings etc. 5/29/2024 | |
| 06/20/2024 | COT - HCBU - Preslab | Not Ready | per previous notes | |
| 07/03/2024 | COT - HCBU - Preslab | Passed |