Parcel: 13313005J


Addresses:

7525 E SPEEDWAY BL


Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Progress  

Permit Number - TC-COM-0423-01051

Inspection Description - COT - HCEL - Electrical Progress  

Inspection Status - Partial Pass

Date Description Inspector Results Comments
03/15/2024 COT - HCEL - Electrical Progress   Partial Pass Feeders to electrical room, building Two, and Athletic field.
04/17/2024 COT - HCEL - Electrical Progress   Partial Pass Conduits for future lighting, scoreboards, and batting cages.
05/06/2024 COT - HCEL - Electrical Progress   Partial Pass Conduits for electrical room Building B.
07/23/2024 COT - HCEL - Electrical Progress   Not Ready
07/25/2024 COT - HCEL - Electrical Progress   Not Ready Wanted UG Electric, but not on permit.
COT - HCEL - Electrical Progress   Partial Pass Looked at Mike-up for Panels ALD1, AL1, AL2, AL3 AL4 and AL5.
Also rooftop.
11/18/2024 COT - HCEL - Electrical Progress   Partial Pass 11/18/24: Electrical rough in is complete on 1st & 2nd level walls. Okay to one-side with drywall and insulate.