Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 03/08/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Stem wall at stairs. |
| 03/13/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1st lift of stairs. |
| 03/15/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
2nd lift at stairs. |
| 03/27/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
3rd lift at stairs. |
| 04/02/2024 |
COT - HCBU - Masonry Pregrout |
|
Canceled |
|
| 04/03/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
4th lift at stairs. |
| 04/04/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
5th Lift. |
| 04/23/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1st Lift Elevator Shaft. |
| 04/24/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
4/24/24: 2nd grout lift of elevator shaft okay to pour. |
| 04/25/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
3rd lift, elevator shaft. |
| 04/29/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
4th lift elevator shaft. |
| 04/30/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
5th lift of elevator shaft. |
| 05/01/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
6th lift. |
| 05/02/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator top out. |
| 05/03/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Stem-wall for Stairwell B. |
| 05/08/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1st lift, Building B, Stairwell. |
| 05/09/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
2nd lift, Building B, Stairwell. |
| 05/10/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
3rd lift, Building B, Stairwell. |
| 05/14/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
4th lift, Building B, Stairwell. |
| 05/15/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
|
| 05/16/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
6th lift, Building B, Stairwell. |
| 05/29/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
5/29/24: 7th lift okay on northeast stairway on all walls of building b. |
| 10/31/2024 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Sit walls for driveway. |
| 12/19/2024 |
COT - HCBU - Masonry Pregrout |
|
Passed |
|