Permit: TC-COM-0326-00402

Parcel: 137010020


Addresses:

5001 S NOGALES HY

Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
08/05/2026 COT - HCEL - Electrical Underground  Partial Pass Partial pass. South soccer field. From 2nd musco lighting pole south west corner. Approximately 70’ of X1 1 1/2” schedule 40 at 24” depth. Up to double box ran along all west end of soccer field to double box at south west corner. Approximately 235’. From double box ran north of soccer field to musco light pole approximately 70’. Olay to backfill all progress areas. Shading required. Ensure caution tape is in place after first lift of compaction. 8/5/2026
08/19/2026 COT - HCEL - Electrical Underground  Partial Pass Home run on the north west side of soccer field C running north to south about 100 feet, OK to backfill and continue with next 100 feet north.
08/21/2026 COT - HCEL - Electrical Underground  Partial Pass 8-21-26: trench depth at 27" to the top of 1 1/2" schedule 40 electrical conduit. Trench runs north to south from the west side of the south soccer field. Okay to backfill approximately 100' of trench using shading materials. Verified depth at 12' on light pole per S9 Schedule which is located at northwest side of south soccer field. Okay for concrete placement
08/25/2026 COT - HCEL - Electrical Underground  Partial Pass 8-25-26: verified a 1 1/2" schedule 40 electrical conduit on west side of soccer field. Conduit runs south to north- okay to backfill approximately 100' using shading materials.
08/27/2026 COT - HCEL - Electrical Underground  Partial Pass 8-27-26: verified trench depth at 28" on a 100' section with a 1 1/2" Schedule 40 electrical conduit. Trench runs south to north on west side of soccer field-okay to backfill using shading materials .
09/03/2026 COT - HCEL - Electrical Underground  Partial Pass 9-3-26: verified trench depth at 28" on a 1 1/2" Schedule 40 electrical conduit located on west side soccer field. Okay to backfill approximately 80' of open trench.
10/22/2026 COT - HCEL - Electrical Underground  Partial Pass 10/22/26: 1" schedule 40 conduit for light poles located on east soccer field-okay to backfill approximately 160' of trench using shading materials.
10/27/2026 COT - HCEL - Electrical Underground  Partial Pass 10/27/26: 1" schedule 40 electrical conduit at east soccer field-okay to backfill approximately 110' of open trench.
10/29/2026 COT - HCEL - Electrical Underground  Partial Pass 10/29/2026 Partial pass. 1” schedule 40 at 26” depth to top of pipe. Point of location near Ramada 2. From light pole north east of playground to light pole next to Ramada. Ran on southeast light pole. Okay to backfill all progress areas. Shading required. Ensure caution tape is in place after first lift of compaction.
11/05/2026 COT - HCEL - Electrical Underground  Partial Pass 11/5/26: verified trench depth on a 1" schedule 40 conduit which runs in an eastern direction from Ramada 2 to north of Ramada 3. Okay to backfill approximately 150' of open trench using shading materials.