Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 08/07/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Furrout for phase one. |
| 08/16/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Phase Seven. |
| 08/23/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
8/23/24: partial for men's restroom phase 2 okay to cover walls. Sub panel okay to proceed and Sheetrock around |
| 09/13/2024 |
COT - LCEL - Electrical Intermediate |
|
Not Ready |
|
| 09/14/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
9/14/24: phase 3 bathroom electrical good to cover |
| 09/20/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Phase Four; break room. |
| 10/16/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Phase Six. |
| 11/05/2024 |
COT - LCEL - Electrical Intermediate |
|
Canceled |
|
| 11/06/2024 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Phase six. |
| 12/04/2024 |
COT - LCEL - Electrical Intermediate |
|
Passed |
|