Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCBU - Masonry Pregrout
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2026 | COT - LCBU - Masonry Pregrout | Passed | Exterior wall from units #34 - 40 complete. Ok to grout progress areas. | |
| 07/23/2025 | COT - LCBU - Masonry Pregrout | Partial Pass | Partial pass. Total of 920' at top out. North side perimeter wall. Okay to grout all progress areas. 7/23/2025 | |
| 09/10/2025 | COT - LCBU - Masonry Pregrout | Not Ready | ||
| 09/11/2025 | COT - LCBU - Masonry Pregrout | Partial Pass | Per Inspection manager, North wall has been added to this permit; working to correct record. Balance of North wall approved; West and South walls remain to be inspected. |
|
| 10/28/2025 | COT - LCBU - Masonry Pregrout | Partial Pass | 10-28-25: verified reinforcement on approximately 640' cmu top out on west wall. Okay for grout on cmu wall at 6'. | |
| 11/24/2025 | COT - LCBU - Masonry Pregrout | Partial Pass | First half of Southside of property |