Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 06/21/2024 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Interior plumbing underground for TI slab. OK to place concrete in progress areas. Ensure slab area is properly termite treated. |
| 06/26/2024 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Plumbing in slab, vapor barrier and rebar is in place. Ok to place concrete in progress areas. |
| 07/18/2024 |
COT - HCPL - Plumbing Progress |
|
Passed |
|