Inspection Status: Passed
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 01/06/2026 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
|
| 08/19/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
8-19-25: plumbing in wall on Building 2-fist floor (minus room 117 & clubhouse) verified per plans-okay to continue with construction at progress areas. Mentioned above rooms together with above ceiling chutes and kitchen exhaust penetrations to be inspected at later date. |
| 08/20/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
8-20-25: Building 2 upstairs units verified per plans. MEP's for clubhouse still required. |
| 08/28/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
8/28/25: plumbing in wall per approved plans. Over notched studs require repair. |