Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 02/03/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
2/3/26: Electrical/mechanical above ceiling approved at rooms 102,103,104,210,205 |
| 03/21/2025 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
See schedule notes |
| 04/02/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric in walls of theater area and projection room. |
| 05/01/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electrical in south wall at concession room 112 and support room 113. Okay to proceed progress areas. 5/1/202 |
| 05/12/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Level #1, Concession/entry area up to leave #2. Ok to insulate and sheet rock interior walls> |
| 05/29/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Theater #4, West wall moved, outlets and switches moved to new locations in wall. |
| 06/03/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Level #2, projection room, ADA restroom, open areas. Ok to cover walls. |
| 07/23/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
7/23/2025 1st floor, both bathrooms and storage area above ceilings approved. Okay to proceed progress areas. |
| 08/11/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
New theater area at levels #1 & 2. Corridors and rooms for possible TCO. |