Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/25/2025 | COT - HCEL - Electrical Underground | Partial Pass | Two floor boxes in pad. X2 4” stubbed out east of building, x1 2”, x2 1” in pad at I.T room. Electrical room conduits in place for two house panels stubbed out south of building. Okay to backfill progress areas. 4/25/2025 |
|
| 05/02/2025 | COT - HCEL - Electrical Underground | Passed | ||
| 08/11/2025 | COT - HCEL - Electrical Underground | Not Ready | 8-11-25: not ready | |
| 08/11/2025 | COT - HCEL - Electrical Underground | Partial Pass | 8-11-25: verified trench depth on 3-2" Schedule 40 electrical conduits for building/subpanel, 1-2" for outside structure & 2-4" primary conduits for SES. Okay to backfill progress areas. | |
| 09/08/2025 | COT - HCEL - Electrical Underground | Partial Pass | 9/8/2025 30' secondary lines from transformer pad to switch gear. Okay to backfill progress areas. | |
| 12/03/2025 | COT - HCEL - Electrical Underground | Not Applicable | ||
| 12/10/2025 | COT - HCEL - Electrical Underground | Passed |