Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
4-1-25, reinforcement on footers per approved plans. Hold downs not in place- Engineer to submit a revision for epoxy. Okay to pour concrete. |
| 04/07/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Not Ready |
Wanted Stemwall, but not on permit. |
| 04/14/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
canopy footings |
| 06/10/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
|
| 06/13/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
South screen wall footings. Ok to place concrete in progress areas. |
| 06/23/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
6-23-25: excavation/reinforcement/prefab trench drain verified per plans for carwash pad. Okay to pour. |
| 06/26/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
6-26-25: top out at south cmu wall okay to grout at 6' 8". Revision was apparently submitted for the extra 8" added to cmu wall. I was not able to locate approved revision so a copy of approval will be emailed to me and possibly the city if not yet reviewed. |
| 07/16/2025 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
|