Inspection Status: Partial Pass
Inspection History: COT - LCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/07/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
5-7-26: approximately 75' of excavation /reinforcement/preslab at north wall CMU footing together with excavation/reinforcement for Control building verified per plans & keynotes. Okay for concrete placement at progress areas. |
| 05/11/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
5-11-26: reinforcement/excavation on approximately 200' of screen wall footing at north, east, and south approved. Okay for concrete placement. |
| 05/13/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
5-13-26: welded wire reinforcement verified at Control Building slab on grade-okay for concrete placement. |
| 05/14/2026 |
COT - LCBU - Building Final |
|
Not Ready |
5-14-26: not ready. Please reschedule at your convenience. |
| 05/15/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
5-15-26: reinforcement at screen wall & at control building verified per plans. Okay to grout 1st lift at 4'. |
| 05/22/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
5-22-26:reinforcement at top out for screen wall & control building approved. Okay to grout. |
| 06/02/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
6-2-26: pre slab/reinforcement at roof of control building approved. Okay for concrete placement. |